Stage 4: Installation of ground level slab

Installation of ground level slab - Schematic drawingColumn head - Schematic drawing

Placing the reinforcement for the ground level slab    Casting the ground level slab

  1. Install dewatering wells.
  2. Scrape 75 mm of piling carpet and lay blinding concrete, formwork and bond breaker to 8.45 m.
  3. Seal/weld sheet piles and form connections to formwork.
  4. Place column capping plates.
  5. Reinforce and cast ground level slab.