Stage 4: Installation of ground level slab
-
Install dewatering wells.
-
Scrape 75 mm of piling carpet and lay blinding concrete, formwork and bond
breaker to 8.45 m.
-
Seal/weld sheet piles and form connections to formwork.
-
Place column capping plates.
-
Reinforce and cast ground level slab.