Stage 8: Forming pile heads and lift pits
-
Place low permeability working blanket.
-
Lay 75 mm concrete blinding over polythene sheet to 1.8 m.
-
Form pile heads, weld reinforcement and connections to pile reinforcement,
sheet piles and steel columns.
-
Seal/weld sheet piles against the ingress of water, down to underside of
lower slab
-
Form pits for the lift system.