Stage 9: Close openings in the upper level slabs

Finishing touches - Schematic diagram

Steel columns and finished sheet pile walls  The finished car park !

  1. Place reinforcement bars and concrete the basement slab to 2.3 m.
  2. Infill openings in upper level slabs with reinforced concrete.
  3. Cease dewatering in stages, decommission and seal dewatering wells.
  4. Check all sheet pile clutches are fully welded and sealed with no seepage.
  5. Sand blast, clean and paint sheet piles and columns.
  6. Outfit underground space for use as car park (e.g. install electrical/mechanical fittings etc.).